Checked
TWC
1.2 MW solar power plant · Tulare County, California
- Operating capacity
- 1.2 MW
- 1 generator
- Main fuel
- Solar
- First unit online
- 2024
Plant details
- EIA plant ID
- 67863
- Operator
- Bravo REC Management LLC
- Sector
- Industrial Non-CHP
- County
- Tulare County
- Balancing authority
- CISO
- Location
- 36.1228, -119.4477
Operating generators
Nameplate capacity and the month each began operating
Swipe the table sideways to see more columns.
| Generator | Fuel | Capacity | Online | Status |
|---|---|---|---|---|
| TWCSolar Photovoltaic | Solar | 1.2 MW | Aug 2024 | Operating |
Nearby power plants
Within 25 miles
Swipe the table sideways to see more columns.
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Tulare 1 and 2 | Solar | 3.0 MW | 5.5 mi |
| Central CA Fuel Cell 1, LLC | Natural gas | 2.8 MW | 5.9 mi |
| City of Tulare Water Facility | Solar | 9.2 MW | 5.9 mi |
| Tulare BioMAT Fuel Cell | Biomass | 2.8 MW | 6.0 mi |
| Cottonwood Solar, LLC (City of Corcoran) | Solar | 12.0 MW | 6.0 mi |
| 1875 West Street Solar | Solar | 2.0 MW | 6.2 mi |
| Corcoran Irrigation District Floating So | Solar | 3.1 MW | 6.6 mi |
| Cid Solar, LLC | Solar | 20.0 MW | 6.6 mi |
Frequently asked questions
- How much power can TWC produce?
- TWC has 1.2 MW of operating nameplate capacity across 1 generator as of August 2026.
- Who operates TWC?
- EIA lists Bravo REC Management LLC as the operator of TWC.
Source: U.S. Energy Information Administration, Form EIA-860M (August 2026) · Data for August 2026